Mid-Marsyangdi earns Rs 14.5b in revenues
The Mid-Marsyangdi Hydropower Project has earned Rs 14.50 billion in revenues since it began operations six years ago.bookmarkThe Mid-Marsyangdi Hydropower Project has earned Rs 14.50 billion in revenues since it began operations six years ago. The 70 MW project was built at a cost of Rs 27 billion, and it has succeeded in recovering more than half of the investment within six years.
Prem Kumari Ghale
Published at : November 15, 2014
Updated at : November 15, 2014 08:54
Lamjung
“Now, it will take at least six years to recoup the rest of the money spent on the project,” said Rajesh Kumar Pandey, chief of the project. Construction started in 2001 and was completed in 2008. The project has been generating 400,000 GW of electricity annually.
Normally, the payback period of a hydropower project is seven to eight years. However, since the Mid-Marsyangdi project’s costs have doubled, its payback period has also doubled. The run-off-the-river hydro project was built with a grant from the German government and investments from the Nepal government and the Nepal Electricity Authority.
Most Read from Money
Goldstar shoes on the brink as India tightens import rules
Three-nation deal signed for Nepal to trade power with Bangladesh via India
Kathmandu’s iconic Annapurna Hotel to be resurrected
Dashain goods stranded on borders of China and India
World Bank unveils $150 million aid for Nepal disaster relief
Editor's Picks
E-PAPER | October 18, 2024
×