Electric power restored in Morang and Sunsari
Power supply has been restored in Morang and Sunsari districts after five days of blackout.bookmark
Published at : August 16, 2017
Updated at : August 16, 2017 08:51
Biratnagar
Power supply has been restored in Morang and Sunsari districts after five days of blackout.
The power supply to the districts was cut off after monsoon – triggered flooding entered the substation building at Sunsari causing considerable damages to the equipment on Friday night.
The water was drawn out of the building through six pumping sets on Sunday. The electric power was restored after tests were carried out on the equipment inundated by the floodwaters.
Although the power supply resumed last night, many places faced power outage from 3 am onwards. The members of the general public here have heaved a sigh of relief following the restoration of power. RSS
Most Read from National
Indian Foreign Secretary Vikram Misri’s Kathmandu visit postponed
Justice Manoj Sharma recommended for chief justice
Nepal keeps protesting over Lipulekh. India and China keep ignoring it
Government set to open competition for ambassador posts, a first in Nepal
Turkish Airlines landing gear fire shuts Kathmandu airport for 98 minutes
Editor's Picks
Nepal keeps protesting over Lipulekh. India and China keep ignoring it
Overexploited for years, the Chure hills are weakening, and water stress is rising across the Tarai
As machines listen, human conversations fade
Why Sanskrit is not dead after all
Lumbini master plan remains unfinished after 48 years
E-PAPER | May 11, 2026
×




22.12°C Kathmandu