Politics
Nepal grants one-year extension to MCC projects
The decision gives the US-funded infrastructure projects more time to overcome delays caused by funding suspension, procurement hurdles and natural disasters.Anil Giri
The government has decided to extend the implementation period of projects under the US-funded Millennium Challenge Account Nepal (MCA-Nepal) by one year.
A few weeks ago, the Cabinet had entrusted the Ministry of Finance with deciding on the extension of several projects, including those jointly funded by the government of Nepal and the US-based Millennium Challenge Corporation (MCC). The decision, however, was not made public in any briefing by the government spokesperson.
“The Cabinet meeting had already entrusted the finance ministry with informing the MCC of its decision to grant a one-year extension to the projects,” a minister told the Post. “We will not bear any additional costs, and the effective implementation period will remain five years.”
The initiative for the extension of the US-funded projects was taken by MCA-Nepal, which submitted a proposal to the ministry in mid-May, requesting it to formally approach the MCC on Nepal’s behalf for an extension of the $747 million compact. The projects include the construction of a 315-kilometre transmission line and the upgrading of a section of the East-West Highway.
The government's decision will now be forwarded to the MCC headquarters for consideration at its board meeting next month.
According to the MCC website, the next board meeting is scheduled for December 8. US Secretary of State Marco Rubio chairs the MCC board.
Some seven months ago, MCA-Nepal had sought the government's approval for a one-year extension, citing multiple disruptions to project implementation. These included US President Donald Trump's decision in July 2025 to suspend foreign assistance and halt MCC payments, leaving the projects in uncertainty for several months before the US administration allowed MCC operations worldwide, including in Nepal, to resume.
“Floods and landslides here also delayed implementation on the ground. After evaluating these circumstances, we have put forward two conditions for the extension,” the minister said.
Of the compact's total budget of $747 million, the United States has committed $550 million and the government of Nepal $197 million. “We have made it clear to the MCC headquarters that we will not bear a single penny beyond our $197 million commitment,” the minister said.
After MCA-Nepal's proposal remained pending at the finance ministry for months, the US Embassy in Kathmandu and senior MCA-Nepal officials took up the matter with Finance Minister Swarnim Wagle and senior ministry officials.
The MCA is a joint initiative of the governments of Nepal and the United States. Nepal is contributing $197 million, while the United States initially committed $500 million through the MCC. In November 2025, the US government announced an additional $50 million grant for the Nepal compact.
The request for an extension followed the Trump administration's brief suspension of MCC operations worldwide after taking office in early 2025, which disrupted project implementation. In January, the US Senate also passed legislation allowing the MCC to extend the terms of its compacts in Nepal, Indonesia, Kosovo and Senegal by up to a year.
Under the MCC compact, the projects are scheduled for completion by August 30, 2028. The legislation states that the Millennium Challenge Corporation may, subject to the availability of funds, extend the eight compacts in the four countries by up to one additional year, provided it notifies the relevant congressional committees beforehand. MCA-Nepal officials say implementation has suffered delays of around 14 months due to the temporary suspension of US-funded assistance and the cancellation and re-tendering of contracts for the transmission line.
“The extension was proposed to make up for the disruption midway through implementation,” said a senior MCA-Nepal board member who is not authorised to speak to the media.
An extension would give MCA-Nepal until August 2029 to complete the projects.
“The MCC headquarters is positive about the proposal because our reasons are well-founded and valid. The Trump administration has also introduced a new law allowing a one-year extension for projects under implementation in four countries,” said the MCA official.
In its letter to the ministry, MCA-Nepal cited several circumstances beyond its control that had affected implementation.
The transmission line component has faced additional delays. In October 2023, MCA-Nepal cancelled the bids for the construction of the 315-km, 400kV transmission line after all bidders quoted prices substantially higher than the estimated cost, forcing it to restart the procurement process.
“Without an extension, neither of the two projects undertaken by MCA-Nepal will be completed by the August 2028 deadline,” said another MCA-Nepal official. An early decision, the official added, would help maintain momentum in implementation and ease pressure to meet the deadline.
MCA-Nepal officials argue that given the frequent delays in completing development projects in Nepal, a one-year extension should not be viewed negatively if it helps ensure the compact's completion.
MCA-Nepal, the agency responsible for implementing the compact, is governed by an executive board chaired by the secretary of the finance ministry.
The five-year compact was signed between the governments of Nepal and the United States in September 2017.
Amid intense political opposition, the compact was ratified by Nepal’s House of Representatives in February 2022. It officially entered into force on August 30, 2023.