Construction of Thapa Khola project expedites
The under-construction Thapa Khola Hydroelectric Project based in Tukuche of Mustang, a trans-Himalayan district in Dhaulagiri Zone of the western Nepal, has witnessed over fifty per centbookmarkThe under-construction Thapa Khola Hydroelectric Project based in Tukuche of Mustang, a trans-Himalayan district in Dhaulagiri Zone of the western Nepal, has witnessed over fifty per cent work progress.
Published at : October 5, 2014
Myagdi
Around sixty-five per cent of the construction of physical infrastructure for the project including a tunnel, dam site power house and power transmission line has been completed. The Mount Kailash Energy Company Private Limited has been granted the contract for developing the project with a capacity of generating 13.6 megawatt of electricity.
The run-off-river type project is going to be developed with complete domestic investment. It is estimated to cost Rs 2.13 billion and expected to complete by within the next one year, company executive chairman Bharat Khadka said.
Most Read from National
Man who set himself on fire outside passport department succumbs to injuries
Ganesh Nepali was fined 1,000 rupees. It cost him his life
Nepal introduces tough rules to rein in educational consultancies, foreign-linked colleges
Twenty-one Pulchowk graduates join Airbus this year
Proposed ‘Romeo and Juliet’ law may spare boys, but what about girls?
Editor's Picks
Proposed ‘Romeo and Juliet’ law may spare boys, but what about girls?
Three prime ministers, 10 premierships. Why is Sudurpaschim still Nepal’s poorest province?
Inside the strange, disciplined, unreachable world of Nepal’s Prime Minister
Three credit booms in three decades ended in economic downturn
How Nepal could lose a generation of footballers due to FIFA’s suspension
E-PAPER | July 19, 2026
×




25.16°C Kathmandu