Construction of Thapa Khola project expedites
The under-construction Thapa Khola Hydroelectric Project based in Tukuche of Mustang, a trans-Himalayan district in Dhaulagiri Zone of the western Nepal, has witnessed over fifty per centbookmarkThe under-construction Thapa Khola Hydroelectric Project based in Tukuche of Mustang, a trans-Himalayan district in Dhaulagiri Zone of the western Nepal, has witnessed over fifty per cent work progress.
Published at : October 5, 2014
Myagdi
Around sixty-five per cent of the construction of physical infrastructure for the project including a tunnel, dam site power house and power transmission line has been completed. The Mount Kailash Energy Company Private Limited has been granted the contract for developing the project with a capacity of generating 13.6 megawatt of electricity.
The run-off-river type project is going to be developed with complete domestic investment. It is estimated to cost Rs 2.13 billion and expected to complete by within the next one year, company executive chairman Bharat Khadka said.
Most Read from National
Balendra Shah intensifies political engagements, meets Lamichhane, Ghising and others
After China, US recalls its ambassador to Nepal
Kathmandu administration denies permission for Gen Z protest, demonstrators dispersed
Students allege British College misled them on ‘overseas courses’
‘Like a dream’: Labourer from Dalit community secures full MBBS scholarship
Editor's Picks
Nepal’s workplaces still fail new mothers
When will Nepali-origin professional footballers in Europe play for Nepal?
‘Like a dream’: Labourer from Dalit community secures full MBBS scholarship
Why Nepal is launching a system to track foreign nationals
Nepal achieves global vaccine target, seven years ahead of schedule
E-PAPER | January 03, 2026
×




6.12°C Kathmandu









%20(1).jpg&w=300&height=200)