Is Nepal’s new Parliament building ready for winter session move-in?
Seven years after construction began, and with the main contract extended six times, the House chamber still awaits tests and handover.Bimal Khatiwada
The construction of Nepal’s new House of Representatives chamber is complete. The entrance leading to it is not.
That mismatch captures the government’s problem as it prepares to hold the winter session in the new building at Singha Durbar, seven years after construction began. The chamber has yet to undergo technical tests or be formally handed over to the Federal Parliament Secretariat, and work on the National Assembly chamber and other parts of the complex continues. The government wants out of the cramped multipurpose hall where lawmakers now meet. The secretariat is not sure it can make the move in time.
Eakram Giri, joint secretary and spokesperson for the Federal Parliament Secretariat, said the lower house chamber needed to undergo technical checks before it could host parliamentary sessions.
“The audio, video and conferencing systems must be tested to ensure they work properly during live parliamentary proceedings,” Giri said. The tests have yet to be conducted because the chamber has not been formally handed over to the secretariat.
The secretariat aims to begin parliamentary proceedings in the new chamber by the end of November. Giri said there would be no obstacles to holding sessions there, provided the facility was handed over on time and passed the required technical tests.
But the entrance to the chamber is still under construction, while work elsewhere in the complex remains incomplete. The secretariat is therefore not yet confident that the winter session can be held in the new building.
Roshan Shrestha, chief of the Special Building Construction Project, said the House of Representatives chamber was ready for use, although work on the National Assembly chamber remained unfinished. The main structural construction across the complex has largely been completed, but interior finishing and other works are still underway.
Overall construction progress stands at 95 percent, Shrestha said. Work slowed during the Dashain and Tihar festivals, while the closure of border crossings disrupted the supply of interior fittings and other materials from China.
The incomplete complex has forced Parliament to continue using temporary facilities seven years after construction began. The multipurpose hall where the House of Representatives currently meets is too cramped for parliamentary proceedings, according to the secretariat. The National Assembly, meanwhile, has been holding meetings in an old Agriculture Committee hall because its designated chamber is not ready.
The Parliament complex is supposed to accommodate four committees under the National Assembly, 10 under the House of Representatives and two joint committees. The shortage of suitable meeting rooms has also made it difficult for parliamentary committees to conduct their meetings.
The project was originally launched to provide a permanent parliamentary complex for the House elected in 2022. The construction contract was awarded on October 3, 2019. But the building remained incomplete even after the House elected in 2026 was formed, forcing the secretariat to hurriedly arrange the multipurpose hall for parliamentary proceedings.
The main construction contract, worth Rs5.67 billion, was awarded to the Tundi-SHEC joint venture. The original deadline was October 2022. After the project failed to meet it, the deadline was extended five times, first to April 2023, then October 2023, April 2024, March 2025 and December 2025. With the work still incomplete, a sixth extension pushed the deadline to February 2027.
Interior work was contracted separately to the KC-Shyamsundar-Baniya joint venture for Rs2.35 billion. The agreement was signed on July 2, 2023, with completion scheduled for mid-July 2024. The deadline was subsequently extended to March 2025, December 2025 and May 2026. After the work remained unfinished, it was extended for a fourth time, to mid-May 2027.
Roofing work, too, remains incomplete. Chainlink Engineering Company secured the separate roofing contract for Rs37.9 million on March 10, 2024. The work has yet to be completed, and the deadline has been extended to mid-May 2027.
Spread across 156 ropanis of land in the Singha Durbar complex, the new parliamentary precinct consists of buildings of up to five storeys. It includes separate chambers for the House of Representatives and National Assembly, a central lobby, offices for senior dignitaries, a library and a museum.
Other structures have been built for parliamentary party offices, parliamentary committees, the Federal Parliament Secretariat, a cafeteria, and press and printing facilities. Infrastructure for parking 476 four-wheelers and 800 two-wheelers has also been completed, along with a building for security personnel.
Dilip Bhandari, director general of the Department of Urban Development and Building Construction, said Speaker Dol Prasad Aryal had instructed officials to prioritise completion of the House of Representatives chamber for the winter session. Construction work had been accelerated following the directive, he said.
“We plan to complete all the work on the building by mid-January 2027,” Bhandari said. Interior finishing and security systems are currently being installed. He attributed some of the delays to the fact that the interior work contract was awarded after the main construction contract.