Long-awaited Ring Road’s Kalanki-Basundhara section widening yet to take off
More than eight years after the project was agreed, work on the 8.2-kilometre stretch has yet to begin as China is still in the process of selecting a contractor.Bimal Khatiwada
The planned widening of the Ring Road’s 8.2-kilometre section from Kalanki to Basundhara has yet to begin, more than eight years after Nepal and China agreed to widen the stretch in 2018. The Department of Roads had most recently expected construction to start after Dashain or October-end, but China has yet to select a contractor.
The project has faced repeated delays, initially because Nepal had not completed the necessary preparatory work and later because the Chinese team had not arrived. Nepal says it has now completed all the preparations required of it.
The two governments first reached a government-to-government agreement in 2018 to widen the Kalanki-Basundhara stretch. A separate implementation agreement was signed on April 29, 2026, by Nepal’s then Infrastructure Development Minister Sunil Lamsal and Chinese Ambassador Zhang Maoming, with the aim of speeding up the project. But construction remains stalled, with officials at the Ministry of Infrastructure Development attributing the delay to China’s failure to select a contractor.
A delegation led by Arjun Prasad Aryal, chief of the Development Cooperation Implementation Division under the Department of Roads, recently visited China for discussions on finalising a wider design. Aryal said the Chinese side was now moving towards selecting a construction company.
“We understand that the project has already received approval from China’s Ministry of Commerce,” he said. “We have been told that the contractor selection process will move ahead once it gets approval from the Ministry of Finance.”
Aryal said the process was expected to be completed within a month, after which the Chinese construction team would come to Nepal to begin preparations.
The design for the second phase was prepared by CCCC First Highway Consultants Co., Ltd. and Xi’an Fangzhou Engineering Consulting Co., Ltd., the Chinese government’s designated consultants for the project. The Department of Roads has also asked them to replace the proposed culvert at Dhungedhara (along the Ring Road stretch) with a concrete bridge. The department had earlier expected China to select a contractor before the monsoon.
China will provide around Rs11 billion in grant assistance for the second phase of the widening project. A Cabinet decision on February 24, 2026, to grant tax and customs exemptions for construction materials cleared another hurdle.
The planned expansion covers only the 8.2-kilometre stretch from Kalanki to a point near Basundhara Chowk.
Under the design, three pedestrian overbridges will be built for people with disabilities: between Sitapaila and Balaju, between Balaju and Machhapokhari, and between Samakhusi and the Basundhara Police Post. China will also install streetlights along the stretch from Kalanki to Basundhara Chowk as part of the project.
The first phase of the Ring Road widening, from Koteshwar to Kalanki, began in 2013 and was completed in 2019.
At present, the road has four lanes between Kalanki and Sitapaila and two lanes on the stretch beyond Sitapaila. The planned expansion will provide an eight-lane road, excluding the service lanes.
Meanwhile, expansion of the roughly 600-metre stretch between Basundhara Chowk and Narayan Gopal Chowk remains held up by difficulties in removing houses and other structures along the road.
China had initially held discussions with Nepali government agencies about widening the Ring Road from Kalanki to Narayan Gopal Chowk. But it backed away after the authorities identified difficulties in demolishing buildings and other structures along the stretch. China later agreed to expand only as far as the Basundhara culvert.
The government has already completed the third phase of the widening work, a 700-metre stretch from Narayan Gopal Chowk to Chappal Karkhana, using its own funds.
A contract has also been awarded to widen the 1.03-kilometre section from Chappal Karkhana to near the Dhobikhola bridge, according to Subodh Kumar Devkota, chief of the Road Division, Kathmandu. Shanti-Sushan JV has been awarded the work with an 18-month deadline.
The contract is worth Rs401.8 million, excluding VAT. The section is currently at the design stage, Devkota said.