Second Mahadevtar tunnel bore breaks through Kathmandu-Tarai Expressway
The 3.445-km tunnel is one of two parallel bores at Mahadevtar. The Kathmandu-Tarai Expressway remains only about 50 percent complete after nine years of construction.Bal Krishna Adhikari
A breakthrough has been achieved in the 3.445-kilometre Mahadevtar tunnel on the Kathmandu-Tarai Expressway, with President Ramchandra Paudel attending the ceremony on Wednesday.
Infrastructure Minister Sunil Lamsal and Chief of Army Staff Ashok Raj Sigdel were among those present.
Two parallel tunnels are being built at Mahadevtar. The bore carrying traffic from Nijgadh towards Kathmandu is 3.445 kilometres long. The breakthrough was achieved in this tunnel on Wednesday.
The other bore, measuring 3.486 kilometres, achieved breakthrough in the third week of August.
The expressway stretches 70.977 kilometres from Khokana in Lalitpur to Nijgadh in Bara. Tunnels account for a combined 11.2 kilometres of the route.
Of the seven tunnels under construction, breakthroughs have already been achieved at Dhedre and Len Danda. Finishing work is underway at both sites. The Dhedre tunnel is 1,691 metres long, while the Len Danda tunnel measures 1,623 metres.
The 2,237-metre Chandram Bhir tunnel has been excavated for 780 metres. Of the 520-metre Sisautar tunnel, 53 metres have been excavated, while 123 metres of the 1,087-metre Devichaur tunnel have been completed. Work on the portal of the 583-metre Mauribhir tunnel is underway.
Nine years after construction was assigned to the Nepali Army, the project remains only about 50 percent complete. Slow construction, land disputes and delays in tree clearance have repeatedly pushed back the completion deadline.
The army was entrusted with the project on August 11, 2017. It was initially scheduled for completion by December 2024. After work fell behind schedule, the deadline was first extended to mid-April 2027 and later to mid-April 2030.
Land acquisition and decisions on the starting point of the expressway and traffic management remain pending along the Khokana-Dukuchhap section. Under the detailed project report, compensation has been assessed, but acquisition is still pending for 69,186 square metres of privately owned land and 7,122 square metres of guthi land. Another 83,939 square metres has yet to be valued.
Of the 89 bridges planned along the expressway, contracts have been awarded for 85 and construction is underway. Contract management for the remaining four bridges in the Khokana section has yet to be completed. Five bridges have already been built. Bridges rising up to 82 metres have been constructed under the project
The estimated project cost, including VAT, is Rs211.93 billion. By mid-September, Rs94.22 billion had been spent, according to the project.